Extra Heavy Duty Load

Extra Heavy Duty Load

L5

To achieve loading figures lintel must be built in with blockwork as shown. Ensure all perpendicular and horizontal joints are filled with mortar. Place mortar bed on top of blockwork before floor units are laid to provide even distribution of load. Steel Lintels may be propped to facilitate speed of construction.


 
 
 

Heavy Duty Load L5 XHD

Heavy Duty Load

L5 XHD

To achieve loading figures lintel must be built in with blockwork as shown. Ensure all perpendicular and horizontal joints are filled with mortar. Place mortar bed on top of blockwork before floor units are laid to provide even distribution of load. Lintels may be propped to facilitate speed of construction.